NEWS EXPRESS is Nigeria’s leading online newspaper. Published by Africa’s international award-winning journalist, Mr. Isaac Umunna, NEWS EXPRESS is Nigeria’s first truly professional online daily newspaper. It is published from Lagos, Nigeria’s economic and media hub, and has a provision for occasional special print editions. Thanks to our vast network of sources and dedicated team of professional journalists and contributors spread across Nigeria and overseas, NEWS EXPRESS has become synonymous with newsbreaks and exclusive stories from around the world.














.webp)




.webp)


.webp)



Loading banners
Loading banners...


National Assembly Complex
Investigation of the National Assembly into the$4.451 billion Nigeria Liquified Natural Gas (NLNG) project 7 has been enveloped in controversies,disagreements and rowdiness from stakeholders.
This happened yesterday in Abuja at the National Assembly during a session held on it by Senate and House of Representativesjoint committee.0 / 1:00
At the sitting yesterday, for twice and for over an houreach, the joint Committees of the Senate and House of Representatives conducting the probe went intotwo separate Executive sessionswith the NLNG officials led by NLNG Project Director, Ali Uwais as well as the contractors handling the project.
At the end of the day, the Committee agreed to formally make their requests known to the NLNG in terms of document and other information needed as it failed to get the requiredinformation.
It also charged theNLNGto halt further variations in the $4.451,731,937 billion contract.
Thursday’s resumed investigative hearing attracted very large crowd of lawmakers comprising members and non-members of the Gas committees because of the hostile atmosphere that has weakened and crippled the investigation since its beginning.
Trouble started when Uwais submitted a document containing what the lawmakers called limited information.
In his remarks,chairman of the joint committee, Senator Jarigbe Agom Jarigbe, PDP Cross River North, howevet expressed disappointment that a clause in the document,clearly said that “figures contained therein are disputed and subject to ongoing legally privileged commercial negotiations”.
Jarigbe said thatit means the figures cannot be used for the investigation.
Amidst the tense situation, the committee went into the first closed door session.After an hour of secret talks, journalists were called in to monitor the situation.
Lawmakers took their turns to condemn the insistence of NLNG and the contractors on not making useful information available for the investigation.
The contentious issues include lack of information and explanation on the original contract sum which was $4,372,760,462.
Others are limited information on the 99 total variation requests worth $177,892,289; approved 62 variation orders amounting to $43,771,475; and approved amendments (claims/settlement) worth $35,000,000.
The NLNG had informed the committee that there are five variation requests being evaluated and they amounted to $7,609,678.
Uwais also told the committee that the fluctuation in foreign exchange rate is a principal cause of contract variation, just as he explained on the status of the project, “The overall progress of the project is at 67% completion, made up of engineering at 97.9%, procurement at 95.5% and construction at 52.5%.
The Committee thereafter adjourned to reconvene on July 3, 2024.(Vanguard)