NEWS EXPRESS is Nigeria’s leading online newspaper. Published by Africa’s international award-winning journalist, Mr. Isaac Umunna, NEWS EXPRESS is Nigeria’s first truly professional online daily newspaper. It is published from Lagos, Nigeria’s economic and media hub, and has a provision for occasional special print editions. Thanks to our vast network of sources and dedicated team of professional journalists and contributors spread across Nigeria and overseas, NEWS EXPRESS has become synonymous with newsbreaks and exclusive stories from around the world.
























Loading banners
Loading banners...


Works Minister Fashola, SAN
The Minister of Works and Housing, Babatunde Fashola, on Wednesday blamed the sit-at-home order in the south east by the Indigenous People Of Biafra (IPOB) for the delay in completion of the Second Niger Bridge project.
Fashola stated this when he appeared as a guest on Channels Television’s Sunrise Daily.
He said: “These dates keep shifting and people must remember that on the eastern side, our contractors have not been able to work on Mondays for almost two years and that has affected the completion date.”
According to the former Governor, while construction workers work on Saturdays, a 52-day loss was a big one in construction work.
The minister further asserted that other challenges like the relocation of transmission lines connecting the East to the West across the Niger River, contributed to days lost and added to the snag that affected the early completion of the bridge within the time earlier stipulated.
Speaking on finishing the last 4km stretch of the road in four months, Mr Fashola said the construction is taking place in a marshland and as such, there is great need for dredging and sand filling, process which he says cannot be rushed.
He emphasized that the reason the ministry and its contractors have made great progress on the road so far, is because they have employed the use of Prefabricated Vertical Drains which accelerate settlement and drainage and as such, workers can start building quicker than would ordinarily have been expected.
The minister however promised that the new target date to deliver a perfectly completed Second-Niger Bridge will be April/May 2023, adding that inevitably the bridge will be tolled to ensure that it is maintained to serve Nigerians for many years.