NEWS EXPRESS is Nigeria’s leading online newspaper. Published by Africa’s international award-winning journalist, Mr. Isaac Umunna, NEWS EXPRESS is Nigeria’s first truly professional online daily newspaper. It is published from Lagos, Nigeria’s economic and media hub, and has a provision for occasional special print editions. Thanks to our vast network of sources and dedicated team of professional journalists and contributors spread across Nigeria and overseas, NEWS EXPRESS has become synonymous with newsbreaks and exclusive stories from around the world.
























Loading banners
Loading banners...


Second Niger Bridge
By KAYODE KOMOLAFE
At least two seemingly contradictory lessons could be learnt from the completion of the first phase of the Second Niger Bridge linking Anambra and Delta states.
On the one hand, the long story of the bridge is a lesson in how not prioritise a project of such a huge significance. On the other hand the completion of the project is agood example of governance as a continuum. It is negative onthe path of progress to delay the execution of such a project with immense implications for so long while it is positive that the Buhari administration elected to end the delay in the building of the bridge.
The iconic bridge was released for public usesix days ago; but there isstill ayet-to- commence second phase comprising the construction of the four kilometre – link roadon the Delta state end and the seven kilometre – road linking the bridge and Onitsha-Owerriinterchange inAnambra state.
As a matter of fact, Works and HousingMinister Babatunde Fashola made this point very clear when he announced two month ago that the bridge would be ready for use before the end of the year.So it’s “a promisekept,” as political publicists would say.
First, the story of the Second Niger Bridge has become proverbial about the levity with whichgovernment takes the provision of very vital infrastructure. The 1.6 kilometre -bridge links the south-south and south east zones of the country.Yet it has beendecadesfrom the time theidea of the bridge was conceived to the completionof the of the first phase of theproject at thecost ofN336 billion to completion The Second NigerBridge had almost become a metaphor for uncompleted projects in Nigeria. The idea of the bridge always came alive during elections. It was an item of campaign towardsthe 1979 presidential election by the National Party of Nigeria (NPN). The election was won by President Shehu Shagari. Hecould not fulfil the promise before the government was overthrown in a military coupafter four years and three months in power. The military regime of General Muhammadu Buhari succeeded the administration of Shagari. Incidentally, it is the administration of Buhari as an elected President that is now completing the first phase of the project. By the way, this is alsohappening two months to another presidentialelection.
At a point, the military regime of President Ibrahim Babangida actually challenged Nigerian engineers to designanother bridge on River Niger to link Asaba and Onitsha. A design was made available, but no bridge was built before the of the regime.
The subsequent military regime of General Sanni Abacha did not make the idea of the bridge a priority.
President Olusegun Obasanjo only remembered the Second Niger Bridgefive days to the end of his eight years in office when he “flagged off” the construction of the bridgein Asaba. Meanwhile the bridge was a campaign issue in the1999 presidential election won by Obasanjo.
Theadministration of President Umaru Yar’aduainherited theproject with the aim of executing it with funds from aPublic Private Partnership (PPP) . In 2007, the cost was estimated at N58.6 billion. A contractor, Gitto, was to provide 60% of the funds while the federal government was to provide 20 per cent while Anambra and Delta states were to be responsible for the rest. The dream was not realised before thedeath of Yar’Adua after three years in office.
Yar’Adua’s successor, President Goodluck Jonathanalso promised to deliver the project in 2015. This was never done despite the fact thatJonathan reportedly told a Town Hall Meeting in Asaba in 2012 that he would “go on exile” if the bridge was not ready by 2015. Ironically, he left office that year.
Meanwhile the huge socio-economic costs of thedelay in thecompletion of the project may never be accurately estimated. The enormous human costof thepressure on the first bridge has also been immeasurable in the absence of an alternative.
Secondly, there is the positive lesson of seeing governanceas a continuum. Three months after his election as president, Buhari cancelled the contracts awarded by the previous administration.A new contract was signed with Julius Berger. The project was managed by the National Sovereign Investment Authority (NSIA) and funded by the Presidential InfrastructuralDevelopment Fund. The other two projects being funded from the same source are the Abuja-Kaduna-Kano Road and theLagos-IbadanExpress Road. These are truly remarkableprojects. The idea of “landmark” projects has been bastardised in Nigeria with culverts, feeder roads and boreholes being “commissioned” with fanfareby some sub-national governments.TheSecond Niger Bridge is not in the class of suchprojects.
Doubtless, the Buhari administration will be leaving office in five monthswithmany important roads dilapidated and several vital bridges not built. The socio-economic landscape is still defined by infrastructural decay. This is a central question in any serious discussion about Nigeria’s development.
Yet, togive the Buhari administration its well-earnedcredit for completing theSecond Niger Bridge is certainly far from giving the devil his due. A number of other roads and bridges are being built. With an undeniable sense of modesty, Fashola draws attention to some of these roads across the country fromtime to time. A lot of progress has been made on the other projects being financed by the presidential infrastructural funding initiative.
What Buhari has done with the Second Niger Bridge is indisputablyan exemplar of a continuum in governance. Abandonment of projects begun one administration by the subsequent governments has become plague in the realm of development at various tiers of government.
While reflecting on the chequered history of the Second Niger Bridge, the rigmarole of constructing the East-West Road which links the states of the Nigeria Delta naturally comes to mind.It is a development tragedy that 16 years after the contract for therehabilitation and expansion of the East-West Road was awarded, the federal government is still the lamenting the poor funding of the project. The Obasanjo administration awarded the contract for the construction of thedual-carriage road with four lanes.The slow pace of work on the project is simply unacceptable.
It is hoped that the East-West Road will benefit from the new creative schemes that the federal government has designedto fund big projects so that this all-important road would be completed early enough for Buhari to “commission” before the end of his tenure. (THISDAY)