NEWS EXPRESS is Nigeria’s leading online newspaper. Published by Africa’s international award-winning journalist, Mr. Isaac Umunna, NEWS EXPRESS is Nigeria’s first truly professional online daily newspaper. It is published from Lagos, Nigeria’s economic and media hub, and has a provision for occasional special print editions. Thanks to our vast network of sources and dedicated team of professional journalists and contributors spread across Nigeria and overseas, NEWS EXPRESS has become synonymous with newsbreaks and exclusive stories from around the world.





















Loading banners
Loading banners...


TCNS General Manager Public Affairs, Mrs Ndidi Mbah
By CONSTANCE ATHEKAME
The Transmission Company of Nigeria (TCN), says the national grid has been restored after a system disturbance, which occurred on Thursday.
The company said that the disturbance occurred at 4:28 p.m. on Thursday with full recovery of the grid achieved by 10:00 p.m. same day.
Mrs Ndidi Mbah, TCN’S General Manager Public Affairs said this in a statement in Abuja on Friday.
Mbah said that according to a report from the National Control Centre (NCC) in Osogbo, the system disturbance was triggered by a significant reduction in generation capacity, primarily due to gas constraints.
”This reduction led to a rapid decline in system frequency. This created a sudden imbalance in the grid.
“The imbalance in grid stability was exacerbated by the sudden tripping of Egbin generation turbine 3, resulting in an additional loss of 167MW load and the subsequent collapse of the grid,” she said.
She said that the grid had since been recovered and was stable, adding that it was currently transmitting all the generated power to distribution load centres nationwide.
She expressed TCN’s unwavering commitment to addressing grid challenges and actively working to mitigate disruptions.
“In instances where challenges extend beyond TCN’s control, the company collaborates with other stakeholders in the power sector value chain to minimise the impact, and swiftly restore the grid to normal operation,” she said. (NAN)