NEWS EXPRESS is Nigeria’s leading online newspaper. Published by Africa’s international award-winning journalist, Mr. Isaac Umunna, NEWS EXPRESS is Nigeria’s first truly professional online daily newspaper. It is published from Lagos, Nigeria’s economic and media hub, and has a provision for occasional special print editions. Thanks to our vast network of sources and dedicated team of professional journalists and contributors spread across Nigeria and overseas, NEWS EXPRESS has become synonymous with newsbreaks and exclusive stories from around the world.









.webp)










.webp)




Loading banners
Loading banners...


By ALEX ENEBELI
Fiscal Responsibility Commission (FRC) has lambasted a contractor, Pitch Global Services that constructed the National Emergency Management Agency’s (NEMA) Southeast Zonal office for executing substandard job.
Dr Chris Uwadoka, Special Adviser to the chairman of the Commission, expressed the misgivings during the inspection and verification of Federal Government’s projects in Enugu State.
Uwadoka who led the Southeast verification team expressed dissatisfaction about the low quality materials used in constructing the building.
According to him, it is disheartening that the building handed over to NEMA only this year has leaking roofs and the ceiling falling off.
“Everywhere in the building is leaking; the finishing is very poor and the whole ceiling is falling off.
“This poses a great threat to members of staff,’’ Uwadoka said.
He blamed NEMA’s management for accepting the building as completed while workers were not comfortable as rain and noise from the roof embarrass them whenever it rained.
He urged the contractor to do the needful or forfeit the 5 per cent retention fee owed it.
Uwadoka explained that the exercise was in line with the mandate of the FRC in ensuring prudence, value for money and accountability as well as transparency in the conduct of fiscal operation.
Reacting to Uwadoka’s stance, the Site Engineer, Pitch Global Services, Engr. Emeka Onyeka, said the building plan which NEMA gave to the contractor was not the original plan.
He said that the building design was later changed which brought about variation in the contract sum.
He added that the roof design was not high roof, adding that increases in the prices of materials affected the quality of the building as estimates in the Bill of Quantity given in 2013 had changed.
Also at the Enugu-Amansea and 9th Mile-Orokam Roads in Enugu, Uwadoka expressed dismay at the level of work done in spite of substantial money the Federal Government had spent on the projects.
The News Agency of Nigeria (NAN) reports that contractors on the projects are Reynolds Construction Company (RCC) and Niger Cat. Construction Company.
Amansea is the boundary between Enugu and Anambra State. (NAN)