Kashimbila Multipurpose Dam ready in Feb. 2015 —Ochekpe

News Express |20th Dec 2014 | 5,943
Kashimbila Multipurpose Dam ready in Feb. 2015 —Ochekpe

The multi-billion naira Kashimbila Multipurpose Dam in Taraba State will be ready for commissioning in February 2015, the Minister of Water Resources, Mrs. Sarah Ochekpe, has said.

Mrs. Ochekpe gave the assurance on Friday during an inspection tour of the project alongside the Ministers of Power and Tourism, Prof. Chinedu Nebo and Chief Edem Duke respectively.

The dam, which will supply 60,000 cubic metres of water daily to over 400,000 people, is now at 95 per cent completion stage.

An excited Ochekpe recalled that the project was just at 10 per cent completion in 2010, noting that the accelerated works carried out on site was a clear demonstration of political will on the part of President Goodluck Jonathan to save thousands of lives that could be endangered should Lake Nyos in neighbouring Cameroon overflow its banks.

Apart from water supply, the Kashimbila Dam has other components such hydro power plant, which will generate 40 mega watts on completion, irrigation with net 2,000Ha, 11 km access road to dam, air strip which is already in use as well as great potential for tourism.

The ministers, who were conducted round the project site by Head of Engineer at S.C.C. Nigeria Limited, the contractor, E Frank, expressed satisfaction with the level of completion and the quality of works done.

Mrs. Ochekpe had this to say: “We are here in Kashimbila today and we are happy at what we have seen. As at 2010, the level of competition of this project was just 10 per cent. But you have seen it has taken political determination of Mr. President to see that this project is executed to finish.

“This is an environmental project that is designed to safeguard the lives of thousands of citizens of Nigeria in more than five states that will be affected should Lake Nyos break.

“We are happy that as we stand here today, the project is at 95 per cent completion. We have already set in motion the processes that will lead to the commissioning of the project in early February 2015. So, we are happy about what we have seen.

“We appreciate all stakeholders that have worked on this project and will continue to work until it’s fully completed. Our greater gratitude goes to Mr. President who has taken it upon himself to see that this project is not just completed but put to effective use.”

On his part, Prof. Nebo was delighted that the turbines for the power plant have already been installed. He said: “This is the most profound use of natural resources and excellent manifestation of world class environmental management. And because of the hydro power plant, the transmission infrastructure that will be put in place here will strengthen the entire Taraba, Benue and Plateau States so that we have a more reliable and stable electricity grid in this part of the country. This is fantastic. This is actually a transformation agenda of Mr. President at work.”

Nebo also assured Nigerians that evacuating the power generated would not be a problem as the contract for putting in place a transmission sub-station and hundreds of kilometres of transmission lines has already been awarded.

Kashimbilla Dam is located between the towns of Kashimbila and Gamovo River Katsina-ala in Takum Local Government Area of Taraba State.

The Dam on completion will check threat of flood from the structurally weak volcanic Lake Nyos along the Cameroon line volcanic activity.

The Minister of Water Resources said should there be flooding, the disaster that ensues will affect Taraba, Benue, Cross River, Kogi and Delta states.

In August 1986, when there was eruption, Cameroon released thousands of tonnes of poisonous gas, which caused extensive flooding resulting in the death of about 1,700 people and 3,000 herds of cattle and livestock.

Also on the inspection tour was the Minister of State for Power, Mohammed Wakili, Permanent Secretaries in the Ministries of Power and Environment and the Director of Dam in the Ministry of Water Resources, Engineer Ikpeawujo, and other directors.

•Photo shows Water Resources Minister, Mrs. Ochekpe and accompanying ministerial colleagues inspecting work at Kashimbila Dam . . . yesterday.

Comments

Post Comment

Sunday, September 14, 2025 6:54 AM
ADVERTISEMENT

Follow us on

GOCOP Accredited Member

GOCOP Accredited member
logo

NEWS EXPRESS is Nigeria’s leading online newspaper. Published by Africa’s international award-winning journalist, Mr. Isaac Umunna, NEWS EXPRESS is Nigeria’s first truly professional online daily newspaper. It is published from Lagos, Nigeria’s economic and media hub, and has a provision for occasional special print editions. Thanks to our vast network of sources and dedicated team of professional journalists and contributors spread across Nigeria and overseas, NEWS EXPRESS has become synonymous with newsbreaks and exclusive stories from around the world.

Contact

Adetoun Close, Off College Road, Ogba, Ikeja, Lagos State.
+234(0)8098020976, 07013416146, 08066020976
info@newsexpressngr.com

Find us on

Facebook
Twitter

Copyright NewsExpress Nigeria 2025