NEWS EXPRESS is Nigeria’s leading online newspaper. Published by Africa’s international award-winning journalist, Mr. Isaac Umunna, NEWS EXPRESS is Nigeria’s first truly professional online daily newspaper. It is published from Lagos, Nigeria’s economic and media hub, and has a provision for occasional special print editions. Thanks to our vast network of sources and dedicated team of professional journalists and contributors spread across Nigeria and overseas, NEWS EXPRESS has become synonymous with newsbreaks and exclusive stories from around the world.


























Loading banners
Loading banners...


By BONIFACE AKARAH
Maryland households could face higher electricity bills and potential power outages as a result of the growing demand from hyperscale data centres unless state regulators strengthen proposed rules governing their connection to the electricity grid, the Office of People’s Counsel (OPC) has warned.
The warning was contained in comments filed by the Maryland utility consumer advocate with the state Public Service Commission (PSC) on Friday, November 13, 2026, urging regulators to tighten proposed “large-load tariffs” for data centres.
People’s Counsel David S. Lapp said recent proposals by major Maryland utilities did not adequately address the costs and reliability risks that new data-centre developments could impose on residential customers.
“The General Assembly has made clear that residential utility customers should not bear the costs associated with new data center load growth. It’s up to the PSC to require changes to the Maryland utilities’ proposals so that customers are fully protected from data center-driven costs,” Lapp said.
The OPC said the proposed tariffs should ensure that data centres bear the costs of studies required to connect them to the electricity system, as well as distribution upgrades and local transmission projects needed to serve their facilities.
It also called for measures to prevent residential customers from absorbing higher regional transmission and energy costs attributable to data-centre demand.
Among its recommendations, the OPC proposed customer-specific charges, calculated surcharges and a “bring-your-own-new-capacity” requirement to protect households from increases in electricity capacity costs caused by large data-centre projects.
It further recommended that data centres post collateral before utilities incur potentially stranded capacity or transmission costs where projected demand is delayed, reduced or does not materialise.
The consumer advocate also called for mandatory curtailment rules requiring data centres to reduce or eliminate electricity consumption during defined pre-emergency and emergency conditions.
According to the OPC, the PSC should also open a separate proceeding to examine how utilities respond to directives from PJM, the regional electricity transmission organisation, to curtail service, including how critical facilities such as hospitals and residential customers would be prioritised during service interruptions.
The major Exelon utilities — BGE, Pepco and Delmarva Power — as well as Potomac Edison and Southern Maryland Electric Cooperative, filed their proposed tariffs in September.
The OPC said its filing includes a comparison of its proposals with those of the PSC staff and the utilities on key features it considers necessary for an effective large-load tariff.
Lapp urged the PSC to act quickly, warning that utilities were already making major decisions in response to requests from prospective data-centre customers.
“The PSC needs to act expeditiously because Maryland utilities are making consequential decisions in response to data center requests for service, including developing construction plans, entering service arrangements, planning investment, and, in some cases, beginning construction,” he said.
The OPC filed its comments as part of the PSC’s ongoing large-load tariff proceeding required under Maryland’s 2025 Next Generation Energy Act and expanded by the 2026 Utility RELIEF Act.