NEWS EXPRESS is Nigeria’s leading online newspaper. Published by Africa’s international award-winning journalist, Mr. Isaac Umunna, NEWS EXPRESS is Nigeria’s first truly professional online daily newspaper. It is published from Lagos, Nigeria’s economic and media hub, and has a provision for occasional special print editions. Thanks to our vast network of sources and dedicated team of professional journalists and contributors spread across Nigeria and overseas, NEWS EXPRESS has become synonymous with newsbreaks and exclusive stories from around the world.

The Nigerian Electricity Regulatory Commission (NERC) on Wednesday ordered owners of private grid-connected transmission substations to register within 45 days.
This was contained in a statement on NERC’s official X handle.
The Order on the Registration and Authorisation of Grid-Connected Private Transmission Substations (NERC/2026/013), effective March 9, 2026, requires operators to secure an Independent Electricity Transmission Network Operator (IETNO) Permit before connecting or operating on Nigeria’s national grid.
NERC said it introduced the framework to bolster grid reliability, safety, and oversight amid frequent transmission line trips flagged by the Nigerian Independent System Operator (NISO).
Key provisions include that NISO must submit a full list of existing Private Transmission Substation Owners (PTSOs) to NERC and notify them within five days.
Current PTSOs have 45 days to apply for the IETNO permit.
New PTSOs must obtain permits prior to grid connection, with sanctions for non-compliance.
NISO will install IoT-based metering at interconnection points within 120 days.
Operators must file monthly reports, with NISO handling inspections.
The Order seeks to improve grid stability and ensure compliance with the Nigerian Electricity Supply Industry’s Grid Code. (The Nation)