FG terminates underperforming Abuja-Lokoja road contracts

News Express |27th Nov 2025 | 171
FG terminates underperforming Abuja-Lokoja road contracts

Dave Umahi, Minister of Works




By ANGELA ATABO

The Federal Ministry of Works has terminated the underperforming Abuja-Lokoja road contracts, following an exhaustive performance review.

The Minister of Works, David Umahi, disclosed this on Wednesday in Abuja, while briefing newsmen on the outcome of the meeting held with the Ministry and selected contractors.

He said the contractors are working on the Lokoja-Shintaku-Dekina and reconstruction of Okene-Ajaokuta road corridor in Kogi state.

Umahi, who was represented by Mr. Mohammed Ahmed, the Director, Press and Public Relations, revealed that some of the contracts were mutually terminated.

He listed the contracts to include: the provision of culverts and drains at flood prone area on Federal Road Network in the North-Central Zone: Section 2, Abuja – Lokoja.

He said the contracts done on rigid pavement are being handled by Messrs Sadogi Nigeria Ltd. was awarded on April 4, 2024.

The minister said that only 39.04 per cent was completed with 112.88 per cent time elapsed.

He said the contract also included the rehabilitation of Abuja – Lokoja Section 4A: CH. 23 + 400 – CH. 26 + 400 RHS in Kogi, being handled by Messrs. Venus Construction Nigeria Ltd.

Umahi said the project, which was awarded on July, 13, 2024, only 33.79 per cent was completed with 131.15 per cent time elapsed.

“There was mutual termination of the contract based on effusion of time.

“The contractor should work within the limit of the advance paid to them after which final determination account is to be carried out,” he said

Umahi also identified the contract for the rehabilitation of Abuja–Lokoja Section IVB (Flooded Section, CH.23+400 – CH.26+395) LHS Contract No. 8490 being handled by Messrs. Sailthrough Engineering Service Ltd.

He said the ministry decided that the contractor should immediately submit a letter of commitment to complete the project on or before Dec.20, adding that the contractor had complied, even when the ministry was owing.

The minister also listed the contract for the reconstruction of Okene-Ajaokuta-Itobe road in Kogi State with contract No. 7648 being handled by Messrs. CCECC Nigeria Ltd.

He said the contract awarded on Nov.18, 2022, only 2.02 per cent was completed with 146.92 per cent time elapsed.

He said there was mutual termination of the contract based on effusion of time.

“The contractor should work within the limit of the advance paid to them after which final determination of account is to be carried out.

“There is also mutual termination of supervisory consultancy services because of lack of funding, has also been directed,” he said.

The Minister said that the Ministry also decided that the contract for the rehabilitation of Lokoja Shintaku-Dekina-Ayingba road, contract No. 7239 being handled by TEC Engineering Company Nigeria Ltd., should go the way of others.

“It was awarded on Feb.3, 2022. Only 1.04 per cent was completed with 188.77 per cent time elapsed,” he said.

He, however, said that the ministry added mutual termination of supervisory consultancy services because of no funding.

He explained that Messrs. Geld/Triacta Nigeria Limited (JV) handling the reconstruction of existing pavement and completion of additional pavement on dualization of the Abuja – Lokoja highways Section III: Abaji – Koton-Karfe has been ordered to resume work within seven days at the bad sections of the road.

The minister commended Messrs. JRB Construction Nigeria Limited for their performance on the rehabilitation works on Section 1 of Abuja – Lokoja road and directed that the project be completed before Dec.10th.

“We have directed that all outstanding works from Abuja to Lokoja, including all to be mutually terminated projects, to be compiled for immediate emergency intervention,” he said

Umahi thanked President Bola Tinubu for his kind interventions on the entire stretch of the 179km x 2 (358km) Abuja-Lokoja Road.

The minister apologised to all road users on the Abuja-Lokoja expressway to bear with the Ministry.

He said the inconveniences being experienced on the road were due to multiple ongoing intervention projects.

He assured that the work would be completed soon. (NAN)




Comments

Post Comment

Thursday, November 27, 2025 9:17 AM
ADVERTISEMENT

Follow us on

GOCOP Accredited Member

GOCOP Accredited member
logo

NEWS EXPRESS is Nigeria’s leading online newspaper. Published by Africa’s international award-winning journalist, Mr. Isaac Umunna, NEWS EXPRESS is Nigeria’s first truly professional online daily newspaper. It is published from Lagos, Nigeria’s economic and media hub, and has a provision for occasional special print editions. Thanks to our vast network of sources and dedicated team of professional journalists and contributors spread across Nigeria and overseas, NEWS EXPRESS has become synonymous with newsbreaks and exclusive stories from around the world.

Contact

Adetoun Close, Off College Road, Ogba, Ikeja, Lagos State.
+234(0)8098020976, 07013416146, 08066020976
info@newsexpressngr.com

Find us on

Facebook
Twitter

Copyright NewsExpress Nigeria 2025